Reasons why the town needs a new police department
Click each box to learn more.
-
We have outgrown all rooms in the current police department, and the evidence room, armory, locker room, and offices do not meet current standards of policing. No space to park cruisers under cover.
-
Safety and privacy are two major issues we face at our current location. We deal with many situations at the dept some create an unsafe environment which is not ideal when the town hall is open. In addition the lack of parking and privacy. Privacy is important to those wishing to report a crime and currently there is none.
-
When the department was first built it met the standard back then. As technology and policy changed we have struggled with keeping up with those standards. Specifically with our evidence storage, armory, training room, and locker rooms. Not meeting the standard for any of these can cause liability issues but also turnover in staff.
-
Officers are currently sharing two work stations for various patrol and investigative work. This slows down officer productivity but also strains officers when reports need to be completed in a timely fashion. Officers are also sharing desks and lockers. Not having enough space for officers to work but also to store their gear is a issue we cant solve in our current department.
-
A combined public safety complex lets our town do more with less. By sharing one site, we cut construction and land costs. It also makes us safer. Co-location means faster coordinated response to emergencies that involve both departments, accidents, fires, medical calls, active incidents.
-
-
Office building: 50' x 80' with two floors, about 8,000 sq ft in total. It has a flat roof and an elevator.
Vehicle bay building: 30' x 80' (about 2,400 sq ft) with a pitched roof. It holds the car port and sally port (the secure vehicle entry), with five overhead doors.
Police-specific spaces: booking, holding, interrogation, juvenile room, evidence, armory, weapons, controlled substances, gear, IT, training, gym, and a patrol room.
Construction type: Pre-engineered metal buildings with metal siding. They are designed for 115 mph winds and 60 psf ground snow load.
The metal building package alone is carried at $325,000.
-
Heating and cooling: Heat pump systems (one per floor) plus a fresh-air energy recovery unit.
Electrical: New underground power service and a 200 kW diesel generator that can run the whole building during outages.
Safety and security: A full fire alarm system, LED lighting, and access control on 27 doors (budgeted at $2,000 per door, about $54,000).
Water: From the existing well. Sewer is a connection per the civil drawings, and the clarifications add a new leach field.
Roof: Rubber membrane with a 20-year warranty on the flat portion, and standing-seam metal on the pitched portion.
-
38 weeks to substantially complete.
The generator and transfer switch have a 35-week lead time, nearly the whole schedule, so they must be ordered early.
The elevator, lockers, and metal building take roughly 12 to 20 weeks.
Work hours are 7am to 3pm, Monday to Friday.
-
The contractor must provide performance and payment bonds for the full GMP amount.
The contractor carries liability, auto, and umbrella insurance ($5 million umbrella), and the Town is named as an additional insured.
-
Utility and entrance fees
Permit fees. The contractor will obtain the permits, but fees are not in the price.
Gym equipment
Builder’s risk insurance (covers the building during construction)
Temporary power and water usage during construction
Landscaping. Only 4" of loam and seed on disturbed areas is included.
Paving of the Priest Road entrance, which is assumed to be done by the Town.
-
Total project price: $4,795,777, which works out to roughly $460 per square foot across about 10,400 sq ft (my estimate from the building dimensions).
Amount
Construction, design, and CM fee subtotal
$4,398,792
Performance/payment bond (premium)
$42,214
Contingency (about 8% of subtotal)
$354,771
Total
$4,795,777
The “Bond” line is the contractor’s performance and payment bond premium, which protects the Town if the contractor fails to finish. It is not the 30-year municipal bond. Please keep the two clearly separate when talking to the public.